← Go Pivot Edge · WorkREPRESENTATIVE MODEL · ILLUSTRATIVE FIGURES

PRICING MODEL · ARCHITECTURE PRACTICE

The fee is set before anyone knows the cost.

An architecture firm agrees a fee months before it finds out what the job takes. This model builds the fee from the hours the work needs, then checks that guess against what really happened.

Margin the year made

4.1%

Against a 15% target

Hours past the estimate

13.1%

56,404 planned, 63,792 worked

Multiplier achieved

2.66x

Fees are priced for 3.00x

What we planned, and what it took

Every job added together, split into the five phases an architecture job runs through.

PlannedActual
05k10k15k20k25kSchematicDesign devDrawingsBidding+36%Site work
Schematic Design+6%
8,462 planned · 8,980 worked
Design Development+8%
11,280 planned · 12,139 worked
Construction Documents+9%
22,560 planned · 24,503 worked
Bidding+1%
2,822 planned · 2,859 worked
Construction Admin+36%
11,280 planned · 15,311 worked

Site work was planned at 11,280 hours and took 15,311. That one phase is 55% of the whole overrun. It happens because the site allowance gets set as a flat share of the fee, and the fee has nothing to do with how many questions a contractor asks.

Nobody logs the Thursday that went on a site query either, so the overrun never shows up until the job closes.

How a job is priced decides what it earns

Same firm, same year, same people. The only thing that changed is how the fee was agreed. Open a row to see the jobs behind it.

Bars run to a 15% target

Fixed fee work earned eight times the margin of work priced off the build cost.

There is a worse problem hiding in that bottom row. Charging a percentage of construction cost pays the architect more when the builder’s costs blow out, and less when everyone does their job well. Everybody in the industry knows this and almost nobody prices around it.

Two changes close the gap

Neither one asks anybody to work harder, and neither needs a difficult call with a client already on the books.

Margin missing against the 15% target$1,202,000
Price site work off the drawing set, not the fee$667,000
Ten contract clauses, four of them a paragraph each$512,000
Left to find$23,000

Open it and break it

Change the overhead rate, drop the multiplier, or switch the scenario to Downside. Every sheet moves with it.

Open the model

11 SHEETS · 605 FORMULAS · NOTHING HARD CODED

Built to show the method. The practice, the projects and the figures are invented so the model can be handed out. The structure is the one that ships. See the rest of the work.